Copyright
Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Please feel free to point to this document. For non-profit purposes you may copy this page, either whole or as whole definitions provided the above copyright notice is attached. For inclusion in for-profit works, please contact the author at maxw@maxwideman.com

File: PMG_F02.htm generated 12/19/2002 9:25:39 AM
Generated by program: PMGlosGen v1.33 Program Author: Graham Wideman

Introduction | What's New in Version 6.1 | International Recognition
About the Author | Sources and References
Content Index |
Order Your V6.1 Copy Here!

Fixed-Duration Scheduling - to - Forward Pass

***  prev

Term
Definition     Editor's Choice
 
Source
Fixed-Duration Scheduling
A scheduling method in which, regardless of the number of resources assigned to the task, the duration remains the same. [D00703]

 WST
Flexibility
The Current FY Budget Allocation less the sum of (Work-to-Date plus Obligations). [D00704]

 PMIS
Flexible
Capable of being easily modified, usually by agreement or under appropriate circumstances. [D02780]

 RMW
Float
The difference between the time available for performing a task and the time required to complete it. If the total float for a task equals zero, then that task is on the critical path. [D00712]

 OTOB 137
Available time for activity execution less time taken by the activity. [D00705]

 NPMT
The amount of time that an activity can slip past its duration without delaying the rest of the project. The calculation depends on the float type. See Start Float, Finish Float, Positive Float, and Negative Float. All float is calculated when a project has its schedule computed. [D00706]

 WST
PMST
Same as Slack Time. [D00707]

 SPM 304-9
See also Free Float [D00708]

  
The full time for an activity during which it can be delayed without delaying the overall program. [D00709]

 CPMUSC 176-8
The additional time available to complete non-critical activities or work items without affecting the critical path (i.e. the total project duration). [D00710]

 CCCP
The amount of time that an activity may be delayed from its early start with out delaying the project finish date. Float is a mathematical calculation and can change as the project progresses and changes are made to the project plan. Also called slack, total float, and path float. See also free float. [D00711]

 PMK96
A measure of the time flexibility available in the performance of an activity. Available in three flavors; Total Float, Free Float and Independent Float. [D03844]

 PNG
Float Trend Charts
A chart showing the progressive change in schedule float. [D02781]

 RMW
Floating Task
A task that can be performed earlier or later in the schedule without, affecting the project duration, [D00713]

 PMK87
Flow Chart
A graphical explanation of a particular process. [D02319]

 DSMC
Flow Diagram
Graphical representation of an information process. [D00714]

 NPMT
FM
See Functional Manager

  
Follow-on Work
Work that is expected to flow as a result of current work. This may be a subsequent project, an enhancement, or the maintenance of the product of the current project. [D02782]

 RMW
Folly
An art form developed by the hide bound in which the same old mistakes are made, but different results are expected. [D03862]

 PNG
Force Account
See Day Work Account [D00715]

  
Forced Analysis
Most PM software can force schedule analysis where a project is re-analyzed even if no new data has been entered. The feature is used for an analysis on the project by itself after it has been analyzed with other projects in multi-project processing (or vice versa). A leveled schedule may also be removed by forcing schedule analysis. [D02254]

 PMST
Forcing
The project manager uses his power to direct the solution. This is a type of win-lose agreement where one side gets its way and the other does not. [D00716]

 PMK87
Forecast
An estimate and prediction of future conditions and events based on information and knowledge available at the time of the forecast. [D00717]

 PMK87
Forecast At Completion ("FAC")
Scheduled cost for a task. [D00718]

 WST
Forecast Final Cost
The sum of committed cost and estimated to complete. See Cost Types. [D00721]

 CCCP
See Estimate at Completion. [D00719]

  
The anticipated cost of a project or component when it is complete. The sum of the committed cost to date and the estimated cost to complete. [D00720]

 PMK87
Forecast Remaining Work
Estimation of the work still to be done to complete a project or activity as of the given cutoff date. [D02783]

 RMW
Forecast Report
A regular report to senior personnel, sponsors and/or stakeholders summarizing the anticipated position of a project in terms of final completion date, cost, scope changes, risks and issues outstanding, etc.
Editor's Note: Progress Report or Status Report is the most common type of project reporting. Unfortunately, this typically misses the point of project management which is to anticipate the conditions at the end of the project and to enable users or customers to plan for the use of the project's products upon completion. [D04478]

 RMW
Forecast To Complete
See Estimate to Complete. [D00722]

  
Forecast to Completion ("FTC")
Forecast To Completion is the cost to completion based upon the actual performance to date and assumes that the rate of expenditure continues as at present i.e. FTC = ACWP x 100 / % complete [D02253]

 PMST
Forecasting
The collection of the latest available information on time, costs, productivity (etc.) to date, as a basis for estimating final outcomes. [D02784]

 RMW
Estimating in advance, trending. [D00723]

 NPMT
The work performed to estimate and predict future conditions and events. Forecasting is an activity of the management function of planning. Forecasting is often confused with budgeting, which is a definitive allocation of resources rather than a prediction or estimate. [D00724]

 PMK87
Foreign
Belonging to another company, organization, nation or country. [D02785]

 Webster
Form of Organization
See Organization Structure. [D02786]

  
Form, Fit and Function Data
Either
  1. For Hardware: Data relating to items, components, processes that are sufficient to enable physical and functional interchangeability, as well as data identifying source, size, configuration, mating and attachment characteristics, functional characteristics, and performance requirements, or
  2. For Computer Software: Data identifying source, functional characteristics, and performance requirements, but specifically excludes the source code, algorithm, process, formulae, and flow charts of the software.
[D03505]

 GAT
Formal
Done according to established custom. [D02787]

 Webster
Done in accordance with official, conventional, or customary form. Done with ceremony. Official and for the record. [D02849]

 RMW
Formal Authority
The ability (of a project manager) to gain support because project personnel perceive the project manager as being officially empowered to issue orders. [D02888]

 PMDT
A project manager's ability to gain support because project personnel perceive the manager as being officially empowered to issue orders. [D02795]

 PMDT
Formal Bid
Bid/quotation/letter/proposal submitted by the prospective suppliers in response to the Request for Proposal, Request for Quotation. [D00725]

 PMK87
Formal Qualification Review
A joint control gate at which the Buyer, based on analysis and test data, determines that the Seller's design will survive the qualification environment as defined in the System Specifications. [D00726]

 VPM 291-4
Formal Reprogramming
See Reprogramming. [D04635]

 QWF
Formative Quality Evaluation
The process of reviewing the project data at key junctures during the project's life cycle for a comparative analysis against the pre-established quality specifications. This evaluation is ongoing during the life of the project to ensure that timely changes can be made as needed to protect the success of the project. [D00727]

 PMK87
QMPP
Forming
The first stage of Team Building where members get to know each other and set up ground rules on behavior. [D03845]

 PNG
Formulation
The process of putting together in a prescribed form. [D02788]

 Webster
Forward Pass
Calculating the earliest start dates moving from left to right along a network. [D00729]

 CPMUSC 176-8
A procedure within time analysis to determine the early start and early finish dates of activities. [D00728]

 WST
Calculation of the earliest start and earliest finish dates on a precedence network. [D00730]

 CCCP
Network calculations which determine the earliest start/earliest finish time (date) of each activity. These calculations are from data date through the logical flow of each activity. [D00731]

 PMK87
The process of calculating the early start and early finish dates of project activities. See also network analysis. [D00732]

 PMK96
Definitions for page F02: 52


***  prev
next  ***

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Top of Page