- Labor
- Any of the following:
- The expenditure of physical or mental effort especially when difficult or compulsory.
- Human activity that provides goods or services
- An economic group comprising those who do manual labor, generally represented by labor unions.
[D02921]
|
Webster |
- Labor Agreements
- Formal contracts between the enterprise and its labor unions. [D02922]
|
RMW |
- Labor Efficiency
- The ratio of earned hours to actual hours spent on a prescribed task during a reporting period. When earned hours equal actual hours, the efficiency equals 100%. [D06038]
|
PMTWG |
- Labor Intensive
- Project activities that have a high content of manual effort relative to production achieved through the use of mechanical equipment. [D02923]
|
RMW |
- Labor Pool
- A pool or agency from which workers can be hired by interested employers. [D02942]
|
PMDT |
- Labor Productivity
- See Productivity. [D03638]
|
|
- Labor Rate Variances
- Difference between planned labor rates and actual labor rates. [D00890]
|
WST |
- Labor Relations
- Those formal activities developed by an organization to negotiate and bargain with its workforce, whether or not that workforce is unionized. [D00891]
|
PMK87 |
- Labor Turnover
- The relationship between employee hirings and separations. [D02943]
|
PMDT |
- Ladder
- Device for representing a set of overlapping activities in a network diagram.
Note: The start and finish of each succeeding activity are
linked only to the start and finish of the preceding activity by lead and lag activities, which consume only time. [D04457]
|
APM BS |
- A sequence of parallel activities connected at their starts or finishes, or both. [D00892]
|
WST |
- Ladder Activity
- A type of activity identified in network scheduling. An arrangement in which two or more series of activities progress concurrently but in lockstep because of dependent links between the same rungs of each ladder. [D02924]
|
RMW |
- Lag
- The amount of time after one task is started or finished before the next task can be started or finished.
Editor's Note: A Lag may have a negative value tied to the finish of a previous activity, reflecting a Fast Track approach. [D00895]
|
OTOB pp271-4 |
- A modification of a logical relationship which directs a delay in the successor task. For example, in a finish-to-start dependency with a 10 day lag, the successor activity cannot start until 10 days after the predecessor has finished. See also lead. [D00893]
|
PMK96 |
- The logical relationship between the start and/or finish of one activity and the start and/or finish of another activity. [D00894]
|
PMK87 |
- The time delay between the start or finish of an activity and the start or finish of its successor(s). See finish-to-finish lag, finish-to-start lag, and start-to-start lag. [D00898]
|
WST PMST |
- Either
- In a network diagram, the minimum necessary lapse of time between the finish of one activity and the finish of an overlapping activity, or
- Delay incurred between two specified activities.
[D04583]
|
APM BS |
- Lag Duration
- A duration by which a given task must be completed before the succeeding activity can begin. [D00896]
|
CPMUSC p176-8 |
- Lag Relationship
- The four basic types of lag relationships between the start and/or finish of a work item and the start and/or finish of another work item are:
- Finish to Start
- Start to Finish
- Finish to Finish
- Start to Start
[D00897]
|
PMK87 |
- Lag Time
- The amount of time delay between the completion of one task and the start of its successor task. [D00899]
|
MSP98 |
- Lagging
- Deliberately setting the start, or finish, of on activity behind the start, or finish, of another. A scheduling technique necessary to enable relatively concurrent progress on more than one activity. [D02925]
|
RMW |
- Laissez-faire Management Style
- A management approach in which team members are not directed by management. Little information flows from the project team to the project manager, or vice versa. This style is appropriate if the team is highly skilled and knowledgeable and wants no interference by the project manager. [D06039]
|
PMTWG |
- LAN
- See Local Area Network
|
|
- Language
- A systematic means of communicating ideas or feelings by the use of conventionalized signs, sounds, or gestures. [D00900]
|
PMK87 |
- Last In, First Out ("LIFO")
- For inventory accounting purposes, the last unit into the inventory is assumed to be the first unit to be drawn out. The inventory value assigned to any unit drawn out is the value of the last unit recorded as still being in inventory. It does not matter which unit is physically drawn out of inventory. See also FIFO. [D03520]
|
GAT |
- Late Bid
- A bid received in the office designated in the invitation for bids after the exact time set for opening. [D03522]
|
GAT |
- Late Dates
- Calculated in the backward pass of time analysis, late dates are the latest dates on which an activity can start and finish. [D00901]
|
WST |
- Late Event Date
- Calculated from backward pass, it is the latest date an event can occur. [D00902]
|
WST |
- Late Finish
- See Latest Finish. [D06319]
|
|
- Late Finish Date
- See Latest Finish. [D06320]
|
|
- Late Finish Time
- See Latest Finish. [D06321]
|
|
- Late Start
- See Latest Start. [D06314]
|
|
- Late Start Date
- See Latest Start. [D06315]
|
|
- Late Start Time
- See Latest Start. [D06316]
|
|
- Latent Defect
- A defect which exists at the time of acceptance but cannot be discovered by a reasonable inspection. See also Patent Defect. [D03523]
|
GAT ` |
- Lateral Communication
- Communication across lines of equivalent authority or between managers at the same level in an organization's hierarchy. [D00909]
|
OTOB p271-4 |
- Lateral Thinking
- A technique used to encourage new and creative ideas without necessarily any logical sequence. [D02944]
|
PMDT |
- Latest Event Time
- Latest time by which an event has to occur within the logical and imposed constraints of the network, without affecting the total project duration. [D04458]
|
APM BS |
- Latest Finish
- Latest possible time by which an activity must finish within the logical and imposed constraints of the network, without affecting the total project duration. [D06325]
|
APM BS |
- The latest time an activity may be completed without delaying the project finish date. [D00903]
|
PMK87 |
- The latest dates by which an activity can finish to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning. [D00905]
|
WST PMST |
- In a network diagram schedule, the latest time at which an activity can be finished. [D00910]
|
SPM p304-9 |
- The latest day a work item can finish without affecting the project duration assuming that all subsequent work items start as soon as they are able and are completed in their expected times. [D00911]
|
CCCP |
- Latest Finish Date ("LFD")
- In the critical path method, the latest possible date that an activity may be completed without delaying a specified milestone (usually the project finish date). [D00904]
|
PMK96 |
- See Latest Finish. [D06322]
|
|
- Latest Finish Time
- See Latest Finish. [D06323]
|
|
- Latest Revised Estimate
- See Estimate at Completion. [D05664]
|
|
- Latest Start
- Latest possible time by which an activity must start within the logical and imposed constraints of the network, without affecting the total project duration. [D06324]
|
APM BS |
- The latest time an activity may begin without delaying the project finish date of the network. This date is calculated as the late finish minus the duration of the activity. [D00906]
|
PMK87 |
- In the critical path method, the latest possible date that an activity may be begun without delaying a specified milestone (usually the project finish date). [D00907]
|
PMK96 |
- The latest dates by which an activity can start to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning. [D00908]
|
WST PMST |
- In a network diagram schedule, the latest time at which an activity can be started. [D00912]
|
SPM p304-9 |
- The latest day that a work item can start without affecting the final project duration. This assumes that it is completed in its expected time and all subsequent work items start as soon as they are able and are completed in their expected times. [D00913]
|
CCCP |
Definitions for page L00: 53
|
|