Copyright
Wideman Comparative Wideman Comparative Glossary of Common Project Management Terms v5.5 is copyright © R. Max Wideman, 2000-2012.

Please feel free to point to this document. For non-profit purposes you may copy this page provided the above copyright notice is attached. For inclusion in for-profit works, please contact the author at maxwideman@shaw.ca

File: PMG_Z00.htm generated 4/14/2012 11:19:39 AM
Generated by program: PMGlosGen v1.37 Program Author: Graham Wideman

 

Introduction | What's New in Version 5.5 | Sources and References
International Recognition | About the Author
Content Index | Order a Copy!

Zero Based Budgeting - to - Zero Float

***  prev

Term
Definition     Editor's Choice
 
Source
Zero Based Budgeting
An approach to corporate, annual plan, budgeting in which all departmental annual budget requirements must be estimated and justified from the ground up, rather than by adding a percentage allowance to last year's approved budget or actual expenditure (typically whichever is the higher.) [D03421]

 RMW
Zero Dollar Contract
A contract, usually for one dollar, that establishes a legal relationship to facilitate transfer of items between the parties. [D04302]

 CSM
Zero Float
A condition where there is no excess time between activities. An activity with zero float is considered a critical activity. If the duration of any critical activity is increased (i.e. the activity slips), the project finish date will slip. [D02172]

 WST
PMST
Describes a work item or activity on the critical path (i.e. a delay in its completion would cause a corresponding delay in the project completion date). [D02173]

 CCCP
Definitions for page Z00: 4


***  prev

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Top of Page