This Guest paper was submitted for publication and is copyright to Jamal Moustafaev, MBA, PMP, © 2013.
Published here August 2014.
The material has been abstracted from Jamal Moustafaev's forthcoming book on Project Scope Management.

Introduction | Quick Overall Outline | The Project Plan Contents
Overview and Recipient Stakeholders | Project Scope Management | Project Quality Management
Project Time Management - Schedule and Milestones | Project Cost Management - Budget
Project Risk Management | Project Human Resources Management
Project Procurement Management | Project Communications Management | Concluding Remarks

Project Human Resources Management

Project Team

List all the project team members as shown in Figure 8. Rather than quoting the persons title in the organization, try to reflect the person's role on the specific project.

Project Role

Name

Project Manager

Brenda Yang

Scope Specialist

Cathy Nadeau

Public Relations Expert

Daryl Leung

Legal Expert

Justin Robinson

Engineer

Michael Moniz

Architect

Paul Sutherland

Foreman

Rob Teves

IT Specialist

Sara Whyte

Figure 8:Responsibility Assignment Matrix (RAM)

It would also be a good idea to assign responsibilities to at least each key task to specific personnel on your project. This will allow the project manager to avoid potential future surprises and miscommunications especially in a traditional functional organization where the resources are assigned by the departmental managers and directors.

Team member responsibilities

Responsibility Assignment Matrix (RAM) is a tabular representation of the project tasks and resources responsible for completion of these tasks (see Figure 9 for a partial RAM).

 

Project Team Members


Deliverables

Project Manager

Scope Specialist

PR Expert

Engineer

Architect

Project Plan

X

 

 

 

 

Scope Definition

X

X

 

 

 

PR Campaign

 

 

X

 

 

Design Documents

 

 

 

X

X

Blueprints and Bill of Materials

 

 

 

X

X

Figure 9: Sample Responsibility Assignment Matrix
Project Risk Management  Project Risk Management