Introduction to Part 2
In Part 1 of this case study, Mark Kozak-Holland
described The Great Escape as a project from a modern perspective of the
project management knowledge areas of PMBOK, specifically scope management. Similarly,
this Part 2 looks at another area of PMBOK, risk
management, and draws lessons in risk analysis, risk response planning, and risk
monitoring and control.
There is little doubt that of the nine project management knowledge areas,
one of the most important to The Great Escape project was risk management. In
today's world some projects never get off the ground because of the perceived
absence of resources, impossible time constraints, or the fear of failure. Often
a Project Management Office (PMO) determines that the risks are too high, and
puts the project on hold.
This part therefore draws lessons in how to identify risk, and what can be
done to make a project more acceptable.
Project Risk Management
Most people are very familiar with the movie The Great Escape but may
not be familiar with it as a project executed in the spring of 1944. The starting
point for the project was in March of 1943 with the move to a new camp, the North
Compound, created to relieve some of the overcrowding in the existing camp. From
the outset the move to and taking up of brand-new quarters would cause confusion
and provide new opportunities, and all sort of possibilities for escape.
Roger Bushell and the escape committee were faced with the conundrum of determining
the best possible approach to an escape. They needed to balance variables like
the availability of resources and the overall risk to the escapers and POWs in
the camp.
In the East Compound the POWs had lost or abandoned at least fifty tunnels
in a thirty-month time frame much to the dismay of the camp's escape committee.
This was a dismal and unsatisfactory track record, and POW morale was sagging
very low. The escape committee (like a PMO) could prioritize the escapes that
had the best chance of success. They could also determine the best Return on Investment
(ROI) for the escape by analyzing the resources and risks for the escape.
Overall there were different types of escapes possible with varying approaches
for example:
- An unplanned and opportunistic escape, where 1 or 2 escapers take immediate
advantage of a presented situation. For example, climb and hide in the back of
a truck inside the camp. These opportunities were extremely rare and risky, and
just to the immediate escapers and not the rest of the camp. In addition, the
POWs had no time to prepare and would end up outside of the camp with no resources
and equipment to continue the escape.
- A planned escape, used once only, a throw away escape where the escape route
would be exposed and could not be reused, for 1 to 3 escapers to get
out. For example, finding a blind spot along the perimeter fence and cutting through
the wire. This would be discovered within 24 hours and was a little less
opportunistic and risky. The POWs would end up on the outside of the camp with
resources and equipment to continue the escape.
- Planned escape, reused several times, for 1 to 10 escapers, several escapes
spread over several months, through a tunnel. There were problems in disguising
missing POWs in the camp for more than a few days. Camp authorities would search
with little let up. Continuation of the project would be very difficult. The POWs
would have resources and equipment outside of the camp to continue the escape.
- Planned mass escape, used once only, a throw away escape where the escape
route would be exposed and could not be reused, for up to 250 escapers to
get out. With many escapers the contribution to the escape would be significant,
the pooling of a lot of materials and resources. The POWs would have good resources
and equipment outside of the camp to continue the escape.
These escape types are further outlined in Figure 4 below:
# |
Number of Escapees |
Approach to Escape |
Description |
Example |
Resources Required |
Risk of Discovery |
1 |
1-2 |
Unplanned, opportunistic |
Take advantage of presented situation |
Hide in the back of a truck |
Low |
Low |
2 |
1-3 |
Planned, used once only |
Escape route exposed |
Cutting through wire |
Med |
Low |
3 |
1-10
at a time |
Planned, reused several times |
Escape route preserved, goal mass escape over long
period |
Simple tunnel |
High |
Very
High |
4 |
Up to 250 |
Planned, used once only |
Escape route exposed mass escape single event |
Well engineered, deep tunnel |
Very
High |
High |
Figure 4: More details of the identified options
|