Throughout every project phase, both Project and Technical Management
must proceed in tandem and be closely integrated.
In this Stage, the 'PCM' is either the prime contractor's manager
or, if trade contracts are let directly, an experienced independent construction
manager. The following tables assume trade contracting.)
Ref #
|
Task
|
Responsibility »
|
OD
|
PD
|
LAC
|
PCM
|
JA
|
3.3.1.0
|
Project
Management
|
3.3.1.1
|
Arrange, chair & minute project team meetings
|
|
|
|
|
|
3.3.1.2
|
Mobilize for construction
|
|
|
|
|
|
3.3.1.3
|
Arrange, chair & minute trade contractor
meetings
|
|
|
|
|
|
3.3.1.4
|
Arrange, chair & minute job foreman meetings
|
|
|
|
|
|
3.3.1.5
|
Establish system of cost control & forecasting
|
|
|
|
|
|
3.3.1.6
|
Establish shop drawing submittal lists
& procedures
|
|
|
|
|
|
3.3.1.7
|
Ensure shop drawing submittals meet master
schedule
|
|
|
|
|
|
3.3.1.8
|
Expedite deliveries (if necessary)
|
|
|
|
|
|
3.3.1.9
|
Obtain schedule updates from trades & suppliers
|
|
|
|
|
|
3.3.1.10
|
Evaluate progress & update schedule
|
|
|
|
|
|
3.3.1.11
|
Establish payment procedures to contractors
& suppliers
|
|
|
|
|
|
3.3.1.12
|
Ensure statutory declarations from contractors
& suppliers
|
|
|
|
|
|
3.3.1.13
|
Approve monthly progress billings
|
|
|
|
|
|
3.3.1.14
|
Administer payment approvals & monthly
accounting review
|
|
|
|
|
|
3.3.1.15
|
Pay consultants, contractors & suppliers
|
|
|
|
|
|
3.3.1.16
|
Report monthly progress, payments, costs
& trends
|
|
|
|
|
|
3.3.1.17
|
Update cash flow scheduling
|
|
|
|
|
|
3.3.1.18
|
Approve Contemplated Changes to the work
|
|
|
|
|
|
3.3.1.19
|
Prepare estimates of costs of changes to
the work
|
|
|
|
|
|
3.3.1.20
|
Coordinate distribution of Change Order
information
|
|
|
|
|
|
3.3.1.21
|
Facilitate settlement of contract disputes
|
|
|
|
|
|
3.3.1.22
|
Administer safety program
|
|
|
|
|
|
3.3.1.23
|
Administer security program
|
|
|
|
|
|
3.3.1.24
|
Deal promptly with labor relations problems
|
|
|
|
|
|
3.3.1.25
|
Arrange inspections by Jurisdictional Authorities
|
|
|
|
|
|
3.3.1.26
|
Establish reasonable dates for Substantial
Performance
|
|
|
|
|
|
3.3.1.27
|
Ensure no liens exist for the work
|
|
|
|
|
|
3.3.1.28
|
Obtain release of holdback documentation
from contractors
|
|
|
|
|
|
3.3.1.29
|
Certify holdback payments as of Substantial
Performance
|
|
|
|
|
|
3.3.1.30
|
Approve holdback payments to contractors
|
|
|
|
|
|
3.3.1.31
|
Make payments to contractors
|
|
|
|
|
|
3.3.1.32
|
Establish reasonable dates for Total Performance
|
|
|
|
|
|
3.3.1.33
|
Verify all deficiencies & outstanding documents
completed
|
|
|
|
|
|
3.3.1.34
|
Approve final payments to contractors
|
|
|
|
|
|
3.3.1.35
|
Make final payments to contractors
|
|
|
|
|
|
At the end of this stage the owner/sponsor has a substantially
completed facility but must still undertake arrangements for the transfer of
the facility to the "care, custody and control" of the facility's operators.
Ref #
|
Task
|
Responsibility »
|
OD
|
PD
|
LAC
|
PCM
|
JA
|
3.3.2.0
|
Technical
Mgt: Construction
|
3.3.2.1
|
Ensure all approvals, permits & licenses
obtained
|
|
|
|
|
|
3.3.2.2
|
Organize access, temporary facilities &
services
|
|
|
|
|
|
3.3.2.3
|
Establish lines, levels & maintain
|
|
|
|
|
|
3.3.2.4
|
Conduct on-going design meetings (if applicable)
|
|
|
|
|
|
3.3.2.5
|
Establish lists of shop drawings & samples
required
|
|
|
|
|
|
3.3.2.6
|
Receive, record and schedule turn-a-round
of submissions
|
|
|
|
|
|
3.3.2.7
|
Review submissions for design requirements
compliance
|
|
|
|
|
|
3.3.2.8
|
Interpret plans & specifications
|
|
|
|
|
|
3.3.2.9
|
Inspect & monitor trade work & conformance
to design
|
|
|
|
|
|
3.3.2.10
|
Select independent testing companies
|
|
|
|
|
|
3.3.2.11
|
Administer quality assurance & control
programs
|
|
|
|
|
|
3.3.2.12
|
Prepare & distribute Contemplated Change
Notices
|
|
|
|
|
|
3.3.2.13
|
Review technical conformance of change
quotations
|
|
|
|
|
|
3.3.2.14
|
Prepare & distribute Change Orders
|
|
|
|
|
|
3.3.2.15
|
Verify monthly progress billings against
actual work-to-date
|
|
|
|
|
|
3.3.2.16
|
Certify extras & credits to contracts
|
|
|
|
|
|
3.3.2.17
|
Certify contractor progress billing for
payment
|
|
|
|
|
|
3.3.2.18
|
Inspections by Jurisdictional Authorities
|
|
|
|
|
|
3.3.2.19
|
Inspect & assess work to verify Substantial
Performance
|
|
|
|
|
|
3.3.2.20
|
Certify Substantial Performance & recommend
releases
|
|
|
|
|
|
3.3.2.21
|
Inspect & assess deficiencies to verify
Total Performance
|
|
|
|
|
|
3.3.2.22
|
Issue Certificate of Total Performance
|
|
|
|
|
|
3.3.2.23
|
Verify all guarantees, manuals, documentation
received
|
|
|
|
|
|
3.3.2.24
|
Certify Total Performance & recommend holdback
releases
|
|
|
|
|
|