|
Table 4: Baseline S‑curve Calculation 1 of 2The second set of calculations are performed for each Day in the Baseline Schedule.
These calculations are shown below.
Table 5: Baseline S‑curve Calculation 2 of 2The Baseline S-curve is constructed by assigning the Baseline dates to the X axis, and the Year To Date (YTD) values to the Y axis. The resulting Baseline Man Hours versus Time S‑curve is shown below. Figure 10: Baseline Man Hours versus Time S‑curvePlease note that the Totals per Day values may be used to generate a Baseline Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown below. Figure 11: Baseline Man Hours versus Time HistogramTarget Man Hours versus Time S‑curveTo generate the Actual and Target S-curves, a Production Schedule is required. For the purpose of this example, the Production Schedule will contain the same five Tasks (one Summary Task, four Detail Tasks) as the Baseline Schedule. Once again, the Summary Task must be ignored to ensure the calculations are accurate. A Production Schedule for the example Project is shown below. Figure 12: Sample Production ScheduleNote this schedule contains the Baseline data from the Production Schedule. This allows Baseline S‑curves to be generated from the Production Schedule. To generate a Target Man Hours versus Time S‑curve, two sets of calculations are performed. The first set of calculations are performed for each Task in the Production Schedule.
These calculations are shown below.
Table 6: Target S‑curve Calculation 1 of 2Target Man Hours versus Time S-curve (Continued)The second set of calculations are performed for each Day in the Production Schedule.
These calculations are shown below.
Table 7: Target S‑curve Calculation 2 of 2The Target S-curve is constructed by assigning the dates to the X axis, and the Year To Date (YTD) values to the Y axis. The resulting Target Man Hours versus Time S‑curve is shown below. Figure 13: Target Man Hours versus Time S‑curve (showing Baseline S‑curve for Comparison)Please note that the Totals per Day values may be used to generate a Target Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown below. Figure 14: Target Man Hours versus Time Histogram (showing Baseline Histogram for Comparison)Actual Man Hours versus Time S-curveTo generate an Actual Man Hours versus Time S‑curve, two sets of calculations are performed. Before these calculations may be performed, the Cut Off Date needs to be defined. This is the date the Project's Tasks were last physically inspected to determine their % complete status. For this example a Cut Off Date of the 4th of February, 2016 will be used. The first set of calculations are performed for each Task in the Production Schedule.
As discussed above in the Target S‑curve calculations, the total Task Man Hours to complete the Task are required. In this worked example, the Production Schedule contains total Task Man Hours. The required calculations are shown below.
Table 8: Actual S-curve Calculation 1 of 2The second set of calculations is performed for each Day in the Production Schedule up to the Cut Off Date.
These calculations are shown below.
Table 9: Actual S‑curve Calculation 2 of 2The resulting Actual Man Hours versus Time S‑curve is shown in Figure 15. Figure 15: Actual Man Hours versus Time S‑curve (showing Baseline S‑curve for Comparison)Please note that the Totals per Day values may be used to generate an Actual Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown in Figure 16. Figure 16: Actual Man Hours versus Time Histogram (showing Baseline Histogram for Comparison)The Baseline, Actual, and Target S-curves may be combined, as shown in Figure 17. Figure 17: Man Hours versus Time S-curves
Home | Issacons
| PM Glossary | Papers
& Books | Max's Musings |