Published here June, 2009.

Introduction | Book Structure | Content

Content

The following are examples of issues with schedules and estimates. Chapter 1 includes the following section:

"Alice in Wonderland

On some projects, stakeholders have conflicting notions about key aspects of the project. This is not just a simple misunderstanding, or a failure to communicate; it is usually the result of ambiguity from the start, allowing different stakeholders to interpret the project in ways that favor their specific position. Because this seems to resolve a crisis and allows the project to proceed, there is no imperative to resolve the ambiguity. Inevitably the crisis is only deferred, recurring later with more significant consequences.

A simple and classic example is the mythical schedule. A mythical schedule is one decreed by a sponsor and acquiesced to by the project manager, but one that cannot be fathomed by any project team member. More prevalent in some corporate cultures than others, the team begins a death march during which the project manager silences any complaint or dispute. Common exhortations include the dictatorial declaration, "The targets are set and it's our job to meet them," as well as the more sympathetic (but equally useless), "Do the best you can." This simple illustration usually has a complex political genesis; however, it does not excuse the project manager from slipping into Wonderland."[3]

Chapter 4 illustrates the subject of Single Point Estimates with the following dialogue:

"Client: 'Hi, thanks for coming over to review your proposal. Please take a seat.'

Consultant: 'Thanks. We made some interesting assumptions as we went through the estimates, and I wanted the opportunity to ensure we're all on the right track. We certainly want this project to be a success.'

Client: 'Yes, of course, so do we. But you won't be doing this project if you can't show a bit more respect for our budget!'

Consultant: 'Well, we've been quite careful to scope this and our local engineers understand your requirements quite well. With the assumptions and risks that we identified, we are prepared to stand behind the fixed price quote you requested. The bottom line was $250K, plus some expenses we can talk about. We understood that within those limits the project showed an excellent cost/benefit and would be approved by the steering committee.'

Client: 'I won't be taking this to the steering committee unless you can justify this price. We weren't expecting anything like this.'

Consultant: 'I'm sorry you're surprised. Last week we reviewed the way our estimates were coming in with your team leader. We told him to expect a range of $230K to $280K.'

Client: 'Joe doesn't understand this company's budgetary process. I have to justify these numbers and they don't fit the departmental allocation.'

Consultant: 'What would you like me to do?'

Client: 'Well, we have to go through the detail, and strip out what's not needed.'

Consultant: 'Actually, we've already done that based on the need/want/wish requirements listed in Appendix A. The estimate is our best shot at making this project a success for both parties.'

Client: 'Sure. So let's see the estimate.'

Consultant: 'The problem is, the estimate is very detailed, and because of uncertainty, I'm sure every line item is open to discussion and possibly disagreement. When we started, you asked us to consider this a fixed-price deal and we agreed, which means we are carrying a fair amount of risk. We rely on our aggregated estimates to work out fairly, even though in the detail some may be higher and some may be lower. Your evaluation of our bid should be based on whether you expect to receive value from our price.'

Client (irritated): 'My evaluation is based upon whether your estimate is sensible. Now let's have a look or we'll have to put this out to tender.'

Consultant (reluctantly): 'Sure, I think I have the details here.'

Client (studies): 'You've allowed excessive time for testing. There is no need for all that project management. Our team leader can take care of most of that stuff plus you've got some padding here!'

Consultant: 'Our test time is based on several very similar projects where that amount of effort was required. We must have a project manager to be responsible for our work if we are carrying the risk of a fixed price. The 'padding' is a contingency number that we include in all our fixed price work to account for a portion of the risk you are asking us to assume. It's based on statistical theory arising from the S curve relationship between the estimate and the ...

Client: 'Take it out!'

Consultant: 'As an alternative, why don't we consider a time and materials approach?'

What is happening here, of course, is a setup for negotiation. This can be very intimidating for a project manager and in a commercial environment the sales representative and the project manager need to have their roles fully worked out in order to cope with this. On their feet, in front of a customer, is not the time for any irresponsible misstep."[4]

We are confident that our readers will be familiar with these scenarios, as we ourselves have been up these avenues many times.

General observations

The content of Ten Commandments of Project Management provides a good reminder of typical every-day challenges that the project manager often faces, and what to avoid - if possible! And throughout, author Robin Hornby attempts to provide experience based advice, and demonstration of proven - as well as some innovative - project management techniques to help meet and overcome the challenges identified. The book is simple and easy to read and considering the price of only $25, shipping and tax included, is good value.

The author may be reached via his web site at www3.telus.net/public/tmi/ or by Email to tmi@telusplanet.net.

R. Max Wideman
Fellow, PMI

Book Structure  Book Structure
 

3. Ibid, p11
4. Ibid, pp74-76
 
Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Search My Site | Site Map | Top of Page