PERT Calculation
PERT distribution assumes a "Beta" probability distribution
- Calculation produces an "Expected time" Te
- Where Te = (To+4Tm+Tp)/6
- That is to say, the Mean Value of the three estimates
- And Standard Deviation
- The mean value is typically higher than the average value
- Because most activities take more time rather than less
- A sophisticated way of justifying a longer schedule