Step 4
Incorporate any "Management Choice" logic
- That is, dates or sequence mandated by management
- These may or may not make sense
- Make sure that management understands the implications of imposed management decisions
- Adjust the logic accordingly
- Always double check that the schedule logic is sound
These Steps 3 and 4 establish the schedule network's configuration