| A Generic Third Level ModelIn searching for a more detailed generic project lifecycle one important
      fact must be borne in mind – that the model should be simple and
      generic. This may sound obvious, but the implications are enormous. The
      generic model is inclusive of all projects, with the exception of the most
      basic, irrespective of their industry sector. Equally, because it is simple,
      most commercial or large-scale projects will be more complex. Thus, projects
      will follow the model in detail and in
      principle, whilst each will have its own more complex lifecycle that should
      be agreed at the outset. But
      where can we find a model to start from? The Chemical Process (CP) industry  has a lifecycle model with seven
      phases; Scoping, Approval, Design, Procurement, Construction, Commissioning
      and Start-up.[5] Many people from other industry
      sectors will no doubt find some similarities to the way the CP industry
      conduct projects. However, the pharmaceutical sector uses an expanded version
      of
      this model that can be seen to split each of the C-D-E-F phases into a
      further two phases each, something that is not immediately obvious from
      the CPI model. Conceive — Discovery and RequirementDefine — Functionality and Design
 Execute — Construct and Check
 Finish — Review and Audit
 At this stage it is best if these terms are defined by an example taken
      from a typical CP industry type project. The definitions are based on the
        theory of how the pharmaceutical sector works rather than any definitive
        practice.
        In
      addition, an indication of the typical stage-gates associated with each
      phase is given. Discovery is often perceived as outside of the project, but is
      the point when the business finds there is a market for product 'A'. Program
        Management might even be said to include a phase prior to this that proactively
        identifies the need
      for 'A', and this does exist outside the project. This phase is brief,
        there are few decisions to be made and the stage-gate for this phase
        is usually
      the marketing department's gut feel. This phase is typically owned by the
        sales and marketing department and in quality function deployment terms
        is the "Voice of the Customer". Requirement is when the business can write a User Requirement
      Specification (URS), which states: "We need X tonnes per year of 'A'
      at a cost of $Y/kg". The stage-gates here may include an assessment
      of the technical feasibility of manufacturing A, the current market prices
      and
      potential profit margins. In the pharmaceutical industry, and others, there
      is an R&D project to identify the means of manufacture of 'A', which
      has a lifecycle of its own. This
      phase is owned by the "business" as the senior representation
      of the operations/production department. Functionality results in the Functional Specification
        (FS) that gives the means/route of manufacture of A and stipulates any
      limitations this imposes, perhaps including preliminary equipment
      selection. The stage-gates at this phase are usually very similar to those
      for final approval of the project budget. This phase is the best for value
      management and "optioneering", but is often "fast
      tracked" and any potential saving locked out of the project. This
      phase is often called "preliminary design/engineering" and may
      involve significant expenditure on major projects. This phase is
      owned by the R&D department and is the first point that the "Voice
      of the Engineer" is heard. Design is the preparation
        of documentation of sufficient detail to allow the suitable equipment
        for the manufacture of A to be
      purchased and built. The stage-gate for the phase is full corporate
      approval of the final project budget. This phase is the remit of the Design/Engineering
        department and where the "Voice of the Engineer" is at its
        loudest. Construct is the purchase and installation of the required
      items. It is notable that in the CP industry model, procurement and construction
        are considered separate phases. This is probably an historic anomaly
        based
        on functional departments. The purchase and installation of all the items
        on
      the project's shopping list is the stage-gate for this phase. It is
      especially important to note that if the project has been divided into
        work packages then each work package can exit the construct stage-gate
      individually. It is the
      division of the project into these work packages that has the potential
        to
      add more phases to a particular project's lifecycle. Also, each work
      package may be a project for a subcontractor, which enters the Discovery
      phase for the subcontractor
      during the main project's Design phase, but reaches its Technical
      Completion (see later for an explanation of this term) by the end of main
      project's Construct phase. This
      phase falls under the auspices of the Project/Construction – clearly
      a misnomer for the Projects department, as this lifecycle indicates. Check is called Installation Qualification (IQ) by the
      pharmaceutical industry and involves ensuring (verifying) that what is
        installed is what was intended to be installed as set out in the design
        documents.
      Also, that installation was done according to those design documents. If
      all items are installed correctly then this phase's stage-gate is
      satisfied. This phase does presume that the design is correct and is not
      intended as a corrective process. This verification (meeting internal
      performance targets – arising from the design) is a fundamental cornerstone
      of the ISO9000:2000 standard and applies to both the Check and Review phases.
      Similar to the Construct phase, separate Work Packages can exit the
      stage-gate independently. Here
      the Design department is often responsible again. Review is referred to as Operational Qualification (OQ) and
      involves testing sub-systems, usually with a test material to ensure that
      the intention of the FS is met. This phase tests collections of equipment
      (systems) to the design intent rather than individual items, as well as the
      interaction of associated systems. For example, can a heating system heat
      the vessel contents in a set time?æ The number of interim stage-gates is
      dependent on the number of levels in the WBS, if it has been formed on a
      systems basis. Here the R&D
      should retake responsibility, even if they do not carry out the activities. Audit is
        called Process Qualification (PQ) and Process Validation (PV), which
        is complete when the project's product can meet the
      stipulations of the URS. The project team decides when Audit is complete
      and this is ultimately a function of customer satisfaction. When the
      customer is satisfied to the mutually agreed standard the project is
      complete. ISO 9000:2000
      defines this as validation, where tests are applied to see if the
      customer's wants are addressed in the "real world". Typically
      there are two customers to keep happy, one is the direct user of the asset
      the project constructs
      and the other the consumer of the asset's functionality or product. At
        this point the Operations department will receive the project at the
        end of
      the phase without the
      exceptional technical support allocated by the "business". These phases described here are the minimum a project lifecycle should
      include. As alluded to above,
      complex projects will need to sub-divide these phases in line with the
      principles discussed below. This is difficult and the only guidance available
        is that Design will have more sub-phases than Functionality which will
        have more than
      Requirement which will have more than Discovery. The same is true, but
        in reverse for Construct, Check, Review and Audit and the basis of this
        is explained below. 
       
 5. Jeffery,
      S., P.E. Harding, "A Crash Course in Project Engineering", pg
      118, Chemical Engineering, July 1995  |