Published here December 2004.

Explanatory Preamble | Brenda Originally Wrote
Louise Responds | Frank Chips In | Kathy … | Quentin Responds
Brenda Tries to Summarize | Max Comments | Glen Responds

Explanatory Preamble

To understand the following discussion you first have to know all the jargon, so here are the explanations for the alphabets soup.

The Earned Value Technique, loosely referred to as "EV" is a project management control tool defined as: "An objective measure of the value of work performed expressed in terms of the budget planned for the work." In other words, what you got for what you spent. The key acronyms are:

EV = Earned Value = percent complete x corresponding budget
BCWS = Budgeted Cost of Work Scheduled, now more properly known as the Planned Value (PV)
ACWP = Actual Cost of Work Performed, i.e. the actual cost
BCWP = Budgeted Cost of Work Performed, now more properly known as the Earned Value (EV)
CV = Cost Variance = earned minus actual = BCWP-ACWP
SV = Schedule Variance = earned minus budget = BCWP-BCWS
BCWS-ACWP = Spending Variance = budget minus actual
BAC = Budget At Completion
EAC = Estimated (cost) At Completion
EAC = variance at completion
CPI = Cost Performance Index = BCWP/ACWP
SPI = Schedule Performance Index = BCWP/BCWS
Combined cost-schedule index = CPI x SPI

You can extrapolate performance to date to calculate the EAC as follows:

EAC = BAC/CPI = BACxACWP/BCWP

This calculation assumes, of course, that the performance experienced to date will continue unchanged to the end of the project. For a variety of reasons it never is and so this calculation is in fact of no practical value.

You can see the relationships of these various elements by going to http://www.maxwideman.com/issacons3/iac1343/sld006.htm

 

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Search My Site | Site Map | Top of Page