Performance Measurement Indices
The foregoing gives rise to several indices
- CPI = Cost Performance Index = BCWP/ACWP
- I.e. Earned divided by Actual
- SPI = Schedule Performance Index = BCWP/BCWS
- I.e. Earned divided by Budget-planned-to-date
- Combined Schedule Cost Index
- VAC = Variance at Completion