Caution !
In addition, most projects
- Involve some activities that are "level-of-effort"
-
That depend on the progress of other activities
- Or are simply a steady overhead
- If the effort involved in these are more than 5-10% of the total
-
Then the EV results could be skewed
- I.e. not be reflecting true performance
The solution
- Is to isolate such activities from the performance assessment