Never use percent complete
Example:
Cost to Date $100,000
Budget $150,000
Apparent Percent Complete 67%
Estimated Cost-to-Complete $125,000
Actual Percent Complete? 44%!
Always re-estimate your forecasts
Here's why
Last 20% of work often costs 50% more !!
No Motivation
Wrong Base