Superdigitation - 2
Example 1
- In an order of magnitude estimate (-25%/+75%)
- A calculated value of $187,654.32
- Could range from $160,000 to $330,000
- Hence a "rounded" entry of $200,000 is appropriate
Example 2
- In a detailed estimate (-5%/+10%)
- A calculated value of $187,654.32
- Could range from $178,300 to $206,500
- Hence an entry of $188,000 or $187,500 is appropriate