Cost Estimate Definitions - 6
Estimate to complete
- An estimate of the cost of doing all the remaining work to complete the activity, work package or whole project
- Based on all the latest information
- Including current productivity rates and trends
Estimate at completion
- The sum of all costs to date and the estimated cost to complete
- A major difficulty is making sure nothing is overlooked at the cutoff date between the two!