What are the practical considerations?
Resource scheduling is not that simple
For example
- You can only redistribute the same resource
- You cannot substitute a different resource
- Unless it has the same skill set
- The project's new end date may exceed the mandated end date
- Resource leveling may change the route of the critical path
- Requiring a recalculation of the schedule network