Monitoring the Schedule - 2
Once work has started and at the end of the first review period
- Record actual start and finish dates
- Of those activities that have commenced
- Or taken place
- Determine progress achieved
- Estimate the time required to complete the on-going and/or remaining activities
- Based on the observed progress
- I.e. The productivity to date