Use software. . .
The last step is much easier using scheduling software
If you examine the values of (ES-LS) and (EF-LF) you will note that:
- The string of activities where these values are zero is the longest path through the network
- This is known as the "Critical Path"
- Where the values are positive indicates that there is "Float" for those activities