What else should I know?
This Baseline Master Schedule should not be changed unless:
- A formal and agreed re-programming takes place
- Of the entire project
- Or a major part of it
- The current actual progress and the target schedule become so far apart that recovery is impossible
- And target objectives have become meaningless
- Such changes are recognized by senior management
- And approved by the sponsor/client