Line of Balance
These charts are more specific and are described as
- A graphical display of scheduled units versus actual units over a given set of critical schedule control points on a particular day, or specific period
- The line of balance technique is oriented towards the control of production activities
- They may be used to advantage where a project includes a long production run
- Such as pre-casting concrete units
- Or prolonged dirt haulage for embankment work
- These charts are not all that common in project work