Critical Path Method
When appropriate data is added to a network
- You can calculate the "critical path"
- Critical Path activities have zero "float"
- And constitutes the "longest path" in the project
Hence, network scheduling
- Is often called the "Critical Path Method" or CPM
The following page
- Shows the idea
- Using the "precedence" display format