Note on Time and Cost
Where a contract
- Calls for a firm fixed completion date
- Such as for a predetermined opening day event
Include space for the contractor to either
- State the cost of acceleration
- As a result of the change
- Or provide for adjustment
- Following subsequent analysis
Similarly
- For "Other impacts"
- This allows for work to proceed without administrative interruption and hassle