Scope or contract change?
It follows that
- A change at the sub-level may or may not be a scope change at the primary level
The example is that of a contractor
- Whose working conditions are spelled out in a contract
If those working conditions change
- But not the final product
- The contractor is entitled to a contract change
- But this is not a change to the project's scope
- Better to call it a commitment change