Aggressive
Schedule
Conservative
Schedule
Uncertain
Outcome
Probability (P)
P = .20
times
Outcome =
Expected
Value (EV)
x + $100,000 = + $20,000
• EV of result = Outcome x Probability of outcome
x - $20,000 = - $16,000
P = .80
EV = $4,000
• EV of decision = sum of all outcomes stemming from decision
x - $20,000 = - $6,000
Uncertain
Outcome
P = .30
x + $10,000 = + $7,000
P = .70
EV = $1,000
• Hence, Aggressive schedule ($4000) is better than Conservative ($1000)
Sum
Previous slide | Next slide | Back to first slide | View graphic version |