WP Rules - 3
Rule 4.
- A WP should have a budget
- Or an assigned value
- In terms of dollars, work hours
- Or priced units
Rule 5.
- A WPs size and duration should be limited to relatively short spans of time
- This will minimize the effort and errors in evaluating work-in-progress
- And forecasts-to-complete