Particulars - 3
The key elements for reporting current project cost status are
- The authorized budget broken down by WBS
- Costs committed-to-date
- Forecast of costs still to be committed
- Hence the Forecast Final Cost
- Variance
- Between the Forecast Final and the approved budget
- And the current Period Variance