Particulars - 2
- Risks within the control of the Project Team should be covered within the Project Budget
- By Contingency Allowances
- I.e. for the "controllable risks"
- Risks beyond the control of the Project Team should not be included in these allowances
- I.e. the "uncontrollable risks"
- These risks should be identified
- And specifically listed as excluded from the Scope of Work descriptions