Particulars - 9
A cost estimate may, or may not, include an assessment of appropriate contingency allowance However,
- A Baseline Budget must include appropriate contingency allowances, and
- A policy on how that contingency will be managed
Estimates at all stages must include all applicable charges such as
- Overheads, on-costs, carrying charges on borrowed capital, etc.